PILOTFÖRSÖK MED KOMBINERAD BIOLOGISK FOSFOR OCH KVÄVEAVSKILJNING / Pilot Plant Studies of Combined Biological Phosphorus and Nitrogen Removal
In november 1990 a new pilot plant for combined biological phosphorus and nitrogen removal was started up at Sjölunda sewage treatment plant in Malmö. So far (May 1991) the pilot plant studies have been focused on simultaneous phosphate uptake and denitrifikation. The results clearly show that it is possible to induce phosphate accumulating bacteria, under realistic circumstances, to use nitrate instead of oxygen for phosphate uptake.
Författare
HANS CARLSSON, ANDERS HILMER and PER JOHANSSON
Årgång
1991
Nummer
2
Sida
139-143
Nyckelord
biological phosphorus removal, nutrient removal.